Thanks to Glenziel and efforts from structural subcontractors, Nirvana By The Sea has achieved 3 floor pours in September which has resulted in the steady progress of the project.
Structurally, the concrete pour is up to Level 10. Unit finishes are now being installed to Level 2 and Level 3. Retail and residential public space facilities are well underway to Level 1 and the Level 2 Podium. Basement parking facilities and ramps are almost complete.
The current program has the structure topping out late January early February 2009. We are currently on target for a planned project completion late Spring 2009.